Home » News » Local News » Michigan » Timeline for 10 projects in District Detroit
Michigan

Timeline for 10 projects in District Detroit

Three years ago, the Detroit City Council approved 10 projects in the District Detroit development — a joint development by the Ilitch organization’s Olympia Development of Michigan and its New York-based partner, The Related Companies.

Had the development been built according to how it was publicly pitched and planned, eight of the 10 projects would be underway or completed by now. So far, however, construction has begun on only one; the others exist only on paper.

Video Thumbnail

The developers have since emphasized that the timelines set out in the original plan were only estimates. Yet those timelines remain the basis for what is currently a spring 2028 deadline for work to at least be started on all the projects.

For now, the developers are staying tight-lipped about when they expect work to begin on the nine projects still to go.

Here is a look at the timelines for each project.

The 10 projects in District Detroit and timeline

Source: The official Transformational Brownfield “Reimbursement Agreement” between the District Detroit developers, the Michigan Strategic Fund, the Detroit Brownfield Redevelopment Authority and the Michigan Department of Treasury, dated Nov. 1, 2023.

Contact JC Reindl: 313-378-5460 or jcreindl@freepress.com. Follow him on X @jcreindl

This article originally appeared on Detroit Free Press: Timeline for 10 projects in District Detroit

Reporting by JC Reindl, Detroit Free Press / Detroit Free Press

USA TODAY Network via Reuters Connect

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

Image

By JC Reindl, Detroit Free Press | USA TODAY Network

Related posts

Leave a Comment